| The teams' first retrospective in Figure {{ref>fig:retro1}} showed the teams' different education backgrounds and speed, the teams' general workload, and the main idea being lost. To fix this the team decided to book a 1-hour meeting where everyone spoke for 5 min and said where they think the project should head. This helped us find common ground. Other conclusions regarding speed and workload: the team decided to meet more often to spread the workload fairly through the team. | The teams' first retrospective in Figure {{ref>fig:retro1}} showed the teams' different education backgrounds and speed, the teams' general workload, and the main idea being lost. To fix this the team decided to book a 1-hour meeting where everyone spoke for 5 min and said where they think the project should head. This helped us find common ground. Other conclusions regarding speed and workload: the team decided to meet more often to spread the workload fairly through the team. |
| |
| <WRAP centeralign> | |
| <figure fig:retro1> | <figure fig:retro1> |
| {{ :report:retrospective1.png?800 |}} | {{ :report:retrospective1.png?800 |}} |
| <WRAP centeralign> | <WRAP centeralign> |
| {{:report:restrospective_8.png?800|}} | {{:report:restrospective_8.png?800|}} |
| | |
| | Retrospective 9 in Figure {{ref>fig:retro9}} was held with Maria absent. The team reported strong technical progress during the sprint: the prototype advanced significantly, the application was successfully connected to the hardware, most sensors were functioning, and the 3D design was completed and ready for printing. The team also received the project components and was finally able to begin working with the physical sensors. Teachers were satisfied with the project’s direction and overall progress. |
| | Several challenges were also identified. Some incorrect components were delivered, which affected the initial electrical system design, and the approaching prototype deadline created additional pressure on the team. Workload distribution was mentioned multiple times as an area for improvement, with some members experiencing a heavy workload depending on their technical background. The team also agreed that communication about weekly progress should improve further. |
| | |
| | <WRAP centeralign> |
| | {{:report:restrospective_9.png?800|}} |
| | {{:report:restrospective_9bis.png?800|}} |
| |
| ==== Summary ==== | ==== Summary ==== |
| |