log [2026/05/18 09:48] – [9th Meeting (2026-05-14)] team3log [2026/06/02 14:17] (current) – [11th Meeting (2026-05-28)] team3
Line 88: Line 88:
  
 Regarding our promotional materials, both the leaflet and poster underwent a thorough review. We are currently correcting minor spelling errors and condensing the leaflet text for better impact. Regarding our promotional materials, both the leaflet and poster underwent a thorough review. We are currently correcting minor spelling errors and condensing the leaflet text for better impact.
 +
 +==== 8th Week Report ====
 +
 +During the 8th week, the team finalized the packaging solution. Our work was focused on finishing the scientific paper and correcting minor spelling errors in our report file. We also received the ordered elements for our prototype, so we have been discussing and deciding how the work should be organized next week to focus on prototype building. During Thursday's weekly meeting, the video of our product was shown. We still have to record the voiceover for the video and standardize the graphics of our final product that we are using in our advertising materials.
 ===== Meetings ===== ===== Meetings =====
  
Line 257: Line 261:
  
  
-==== 9th Meeting (2026-05-21) ====+==== 10th Meeting (2026-05-21) ====
 === Agenda: === === Agenda: ===
   * 3D printing   * 3D printing
Line 265: Line 269:
   * packaging solution   * packaging solution
  
 +During our last meeting, we finalized the next steps for the prototyping, testing, and documentation phases of the project.
  
 +Regarding manufacturing, the team must immediately complete the preparations for the 3D printing process and submit the final design files to production. To assist with the physical assembly of this prototype, we have been provided with new LEDs that need to be integrated into the build.
 +
 +In terms of testing and quality assurance, two major evaluations are required. First, the water bottle must undergo a theoretical load and stress test to ensure its structural integrity. Second, we need to conduct usability testing for the mobile companion application to optimize its user experience.
 +
 +Significant progress was also mapped out for our documentation and packaging materials. We decided that the text for the packaging solution needs to be shortened and streamlined. Furthermore, the user manual must be thoroughly proofread to eliminate any typos and grammatical errors, while also being revised to make the content more concise and precise.
 +
 +Finally, we addressed the academic paper. The team was given instructions to carefully review all sources and references within the document, adding page numbers where they are currently missing. To complete the paper, all remaining chapters must be fully drafted and integrated as soon as possible.
 +
 +==== 11th Meeting (2026-05-28) ====
 +=== Agenda: ===
 +  * App presentation 
 +  * Paper 
 +  * Functional Tests & Results
 +  * UV-C light testing 
 +
 +=== Minutes: ===
 + The submission of paper postponed to 5th June. 
 +Put results of the functional test on Wiki.
 +Think about making simulation if impact/stress test when for example kid will kick the bottle.
 +UV-C light may be tested in special Lab, and the test will be conducted and we will be notified if it's working. 
 +In paper the picture of bottle should be change to the latest one.
 +In paper fig 2. App deigned instead of TRAQUA design.
 +The illustration of packaging solution may be connected with picture of the bottle to not have that many picture in the paper.
 +Put two imagine, and put picture of load stress. 
 +Change Erasmus Project Semester to European Project Semester. 
 +
 +==== 12th Meeting (2026-06-03) ====
 +=== Agenda: ===
 +  * Protection glasses
 +  * Battery issues 
 +  * Summary of paper
 +  * Scheme of final presentation 
 ===== Activities ===== ===== Activities =====
 //Please register here all accomplished project activities// //Please register here all accomplished project activities//